Define fields in P6.
- Created
- 2
- 2
Hi Guys,
Trust you are doing good. I am trying to define a field in P6 and make P6 calculate its value in the future like we can in excel.
I know how to define a user field and classify it as a number/start date/integer etc., but is it possible to put in a formula in P6 that will do calculations for that field?
Example: If my User field = Preparation for start date; I want this 'preparation for start date' to always be 2 days before the start date of an activity. Is there a way to store a formula in P6 that will do Start date - 2 days = preparation for start date and display it in the customized field?
Thanks a lot,
Akhilesh.