Resourcing using various calenders
- Created
- 8
- 5
Hello
Please can someone help me!! I am working with P6 and have come accross a problem that I am stuck with at the moment. Apologies if this has been asked before I have had a quick look through past activities but cant find the same problem and not to sure how to do a search?
I have a schedule where I have added activities and where certain activities have various resources attached to the same activity.
ie Task 1 total 15 days (based on a mon-friday calender) I have attached a resource which also uses the same calender but I have also attached a resource which has a 6 day week or mon-sat calender and I want to show both resource on the activity but one working for 15 units (based on 3 x 5 day weeks) and the other using 18 units (based on 3 x 6 day weeks)
Is this possible? Do I need to make the activity based on the larger 6 day week or am I going wrong somewhere else?
Thanks in advance for any help!
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?