percent complete

Dave EllisMember for 20 years 5 months
Created
2
1
0

Is it possible to use weighting for rolled up performance % complete.

I have noted that as long as the budgeted units >0 then performance % complete rolls up. However the performance %complete does not change whatever the number of units is e.g. if 2 activities have 1hr each the rolled up percent complete is the same as if 1 activity has 1hr and the other has 1000hrs.

Can anybody help?

2 replies

Oldest first
  1. 0
    Arend Kok ·

    Hi Dave.   Performance

    Hi Dave.

     

    Performance percent complete uses the Total cost per activity as a weighting.

     

    So the answer lies in your resource rates. If you use a rate of 1$/h you are then effectively using your budgeted units as a weighting.

  2. 0
    Dave Ellis ·

    Thanks Arend

    Thanks Arend