Primavea 6.2.1 callenders

Mark DunnMember for 16 years 1 month
Created
0
2
0

I have a schedule with a base callender of 8hrs per day.  when I add activities and give them a specific callender of 24 hrs per day I have to enrter 3 days into the duration column to get 1 day between the early start/early finish dates.  Does anyone have any idea how to solve this?  Thanks, Mark