Good day, I use MS project and currently try to move to Primavera. 
But there are some things that I can't do in Primavera. 
For example in linked photo ( http://imgh.us/MS_Project.jpg ) you can find screenshot from MS project where I allocated resource to activity and entered planned work load by every day and then entered actual work for every day.
So I can see on which date I worked more and what was total plan/actual work. But I can not do the same in Primavera. 
The only thing I can do is to enter planned work for every day. Or enter number of days and let Primavera distribute work hours based on Curve I select. I can't enter actual work for every day only remaining part. So that means can only see in total what was overwork for example and for daily tracking I have to use excel.

May be I do not know something and you can help me with that?
 
 
 
http://imgh.us/MS_Project.jpg

3 replies

Oldest first
  1. 0
    Zyman Sergio ·

    http://imgh.us/MS_Project.jpg

    http://imgh.us/MS_Project.jpg

  2. 0
    Zyman Sergio ·

    Thanks in advance

    Thanks in advance

  3. 0
    Zoltan Palffy ·

    if you select Project

    if you select Project Resource assignments

    then ontop on the right click the time scale choose and Week/Day1

    the also on the right click on the small upside down triangle and choose spreadsheet fields and select Actual Units

    now you can do the same thing as in MS Project 