Primavea vs MS Project
In the Open Standard
Zyman SergioMember for 11 years 6 months
- Created
- 1
- 3
0
Good day, I use MS project and currently try to move to Primavera.
But there are some things that I can do in Primavera.
For example in attached photo you can find screenshot from MS project where I allocated resource to activity and entered planned work load by every day and then entered actual work for every day.
So I can see on which date I worked more and what was total plan/actual work.
But I can not do the same in Primavera. The only thing I can do is to enter planned work for every day. Or to enter number of days and let Priavera distribute work hours based on Curve I select.
I can't enter actual work for every day only remaining part. So that means can only see in total what was overwork for example and for daily tracking I have to use excel.
May be I do not know something and you can help me with that?
Thank you.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?