Earned Value - At Completion values with Current dates

Haresh JayanthMember for 20 years 1 month
Created
2
2
0

Dear All,

In Admin Preferences , Earned value tab , we have 3 methods to choose earned value

1) Budget value with Planned dates.

2) Budget values with Current dates.

3) At completion value with current dates.

I have a clear idea the use of the first two. But i want somebody to explain what is use of having " At completion values with current dates to compute Earned value management.

Pls help.

 

regards,

 

Haresh Jayanth - PMP

2 replies

Oldest first
  1. 0
    Dinesh Kumar ·

    1) Budgeted value with

    1) Budgeted value with planned dates

    PV = budget value x time spread or budget value x cost spread

     2) Budgeted value with current dates

    PV = budget x current elapsed duration / total duration with expected completion

    3) At completion value with current dates

    PV = EAC x current elapsed dur / total dur with expected completion

  2. 0
    Zoltan Palffy ·

    the key wording here is the

    the key wording here is the 1st word Budget of the 1st 2 options the 3rd option is AT completion which could be more or less than the budget.

Log in or join to reply