Copy a WBS from EPS to Another EPS

Gobinath NarayanasamyMember for 17 years 7 months
Created
1
2
0

HI Friends

How to copy a WBS from one EPS project to another EPS project.

and i want know that possible to view all project(whatever in the database) in WBS layout mode.

1 reply

Oldest first
  1. 0
    Gary Lister ·

    Hi Just right click on the

    Hi

    Just right click on the WBS and select copy

    to view all projects it will depend on your computer memory but yes this is possible but it will show nothing except wbs codes

Log in or join to reply