Copying external logic from reflection or XER copy into original project?

Carlos NazarioMember for 17 years 8 months
Created
2
2
0

We removed hundreds of links between activities in two different WBS's. Now we realize that wasn't the right move and need to re-link everything.

The first thought is to do it maually, which will take a while. However, before removing the links I had created a copy (XER) and a reflection of the project. Is there a way I can r bring the activities and all their links (internal and external) from either the XER copy or the reflection into the source/current project?

Thanks.

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi Carlos, Try this simple

    Hi Carlos,

    Try this simple steps to get back those lost relationships.

    1. Open the Project where the links are present.

    2. Add the Project in which you removed the links as a Baseline Project.

    3. From the Maintain Baseline windows click the Update then select the items you would like to add or remove into the Baseline Project.

     

    Hope this will help you.

     

    Regards,

     

    Raymund

  2. 0
    Ghulam Haider ·

    Very Nice Mr. Raymund, it

    Very Nice Mr. Raymund, it solved my issue. Thanks a lot.