How to know target Percentage for the next week ?

Irfan KhanMember for 17 years 3 months
Created
2
5
0

Hi to all expertise,

I have updated my schedule now the over all progress is 12.67 % on data date 15-01-2011.
I want to know target percentage for next week of my each WBS as per assinged baseline..

how to show these percentage ?

please need help,,


thanks,,,,,
 

2 replies

Oldest first
  1. 0
    Kumar S ·

    Dear Irfan, if you want  to

    Dear Irfan,

    if you want  to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..

    like this you can get the % complete for the future periods...

     

  2. 0
    Kumar S ·

    Dear Irfan, if you want  to

    Dear Irfan,

    if you want  to know the target complete % for the next week then go to the projects window there in the dates tab change only the Data Date to the next week but do not schedule..

    like this you can get the % complete for the future periods...

     

Log in or join to reply