Remaining Labour Unit Calculations
In the Open Standard
Andrew TanMember for 22 years
- Created
- 0
- 3
0
Hi,
Was trying to get the remaining labour units out. And as follows
Budgeted Labour Units = 16,804,352
Earned Value Labour Units = 5,235,908
Actual Labour Units = 2,696
Remaining Labour Units = 13,151,437
How do I get Remaining Labour Units = Budgeted - Earned?
Thanks,
Adnrew