linked milestone

Juan L. Ramos L.Member for 16 years 4 months
Created
1
2
0

Dear,

 

I have the following questions.
milestones to be linked with a final milestone necessarily?
I am doing a Schedule that when linked the final milestone milestones and critical path shows only the final milestone, despite the fact that there are activities that have zero total Float. However when I leave to join if I show how critical path activities with zero total Float. I do not want to warnings showing

http://rapidshare.com/files/453232756/Tunel_de_Quellaveco_Rev14.xer

http://rapidshare.com/files/453232986/Tunel_de_Quellaveco_Rev14_sin_warnings_.xer

Saludos,

JL

1 reply

Oldest first
  1. 0
    Juan L. Ramos L. ·

    Dear, Solve the problem by

    Dear,
    Solve the problem by establishing a relationship FF intermediate milestones milestone Final

    Regards,

    Juan Luis