Purchase P6 Contractor or P6 Professional

Cawboye MaseMember for 19 years 8 months
Created
1
0

Evening All, beside limitations to number of activities are there any issues with going with P6 Contractor, small company (myself), or should I bit the bullet and go all in, also is there any reason to wait on a upcoming version

Thanks                rmason_ns@yahoo.com

1 reply

Oldest first
  1. 0
    Paul Harris ·

    Primavera Contractor has a

    Primavera Contractor has a few other issues in a multi user environment as each user has their own database loaded on their own machine. You have to export a file in XER format to give it to someone else a project. You would also have to export layouts if you want some one else to use you layouts.

    You also can not copy and paste activities between one project and another.

    Primavera Contractor is basically a hobbled copy of P6.

    I recommed you buy P6 and not Contractor unless you only have an occasional project to create and you do not need to share projects with other in your company.

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au - a Primavera scheduling software resources site

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?