Performance Percentage Completion ?

Shah. HBMember for 17 years 10 months
Created
7
4
0

Hi

 

Performance percentage completion: On updating the P6 Program of works monthly (Feb 2011 to Mar 2011)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

 

Regards

Shahul

7 replies

Oldest first
  1. 0
    Erdem Eminol ·

    Hi Shahul, Performance

    Hi Shahul,

    Performance percent complete depends on % complete type. Please check there is any change on that fo activities or not.

  2. 0
    Gary Whitehead ·

    have you added any new

    have you added any new activities since last month?

     

    how are you measuring % complete?

  3. 0
    Andy Power ·

    You must have added new

    You must have added new activities or more value in to the programme?

     

    At summary level performance % complete is (BCWP * 100) / BAC.

     

  4. 0
    Shah. HB ·

    Hi to all Many thanks for

    Hi to all

     

    Many thanks for your valued response

    @Gary

    No new activities are added.Baseline program is cost loaded .Performance percentage is used for measuring actual field progress through feeding physical percentage in to the activities

    @Erdem

    I agree with your statement .I did the same and increased the activity percentage as they advance over a month time period .In the end I got strange result is that decrease in percentage when compared with last month.

    @Andy

    Adding new activity too, remains pointless

     

    Please advise.

  5. 0
    Kamarul Bahrin Hassan ·

    Hi... try to check, did you

    Hi...

    try to check, did you attached the baseline and assign baseline ?

    tq

  6. 0
    Daniel Limson ·

    Shahul, There is no other way

    Shahul,

    There is no other way but to check activity by activty and comparing it to your last months report, i am sure you can find anomalies. you can do a quick check by filtering activities completed and activities in progress.

    Regards,

    Daniel

  7. 0
    Shah. HB ·

    Thanks to all,the issue got

    Thanks to all,the issue got resolved 

    Regards

    Shahul

Log in or join to reply