Logic and Saving issue in P6
- Created
- 1
- 3
Hi P6 experts,
I once again need your urgent help on the following, Please help me out.
a) For updating the progress of Building Projects which is best option
Retain Logic or progress override
Some said that progress override is best for that but I think retain logic is Ok. Please suggest me which is the best?
b) How to link the activties too quickly in a lengthy programme. In 2000 actvities programme what is the best way to link the activities in a quickest way? Any tip or trick, please mention. pdf will be great if available.
c) P6 saves the files automatically. Any tip or trick to stop it autosave during changes in progarmme?
d) In P6 version 6.2 , for creating horizontal tiles view of 2 programmes, I could not find Horizontal Tab Group in View option. How to view 2 progammes in horizontal tiles view in that version. Please suggest.
Thanks
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?