Remain Finish Date vs Remain Start Date.

Jean DesjardinsMember for 15 years 3 months
Created
2
3
0

Hi everyone,

I am using Primavera PM6 to manage the coming workload of our team.

We have about 95 projects in progress with 4 to 9 activities in each project.

My problem occurs when I open many projects at the same time, the remaining units of some tasks are offset later in timescale and when I try to change the finish date, I get this message :

"Remain Finish Date cannot be earlier than Remain Start Date."

If anybody experienced the same problem, I would appreciate your help.

Thank you

Jean D

2 replies

Oldest first
  1. 0
    M Carey ·

    I also get this error when I

    I also get this error when I have only one project open. In addition, I get another error that referes to the Remaining Start and Remaining Finish: Remaining Start cannot be Null; Remaining Finish cannot be Null.

  2. 0
    Ravi Katare ·

    HiInsert two columns1. Early

    Hi

    Insert two columns

    1. Early Remaining Start & 2. Early Remaining Finish.

    For any Inprogress activity, ensure that Early Remaining Start < Early Remaining Finish. If not do it manually by selecting the customize date.

    PS: dont forget to move data date after applying the actuals, its cause such kinda problem.

     

    - Ravi