Task with linked start and finish dates
In the Open Standard
Kate NashMember for 15 years 3 months
- Created
- 2
- 4
0
I need to put a task into a plan which starts on the date a predecessor finishes, and ends on the date a successor starts.
For example, the tasks I have are:
Handover to Client - Finish Milestone 1st December 2011
Rental Period
Handback from Client - Finish Milestone 31st December 2011
The Rental period needs to automatically show the start date as 1st December and the end date as 31st December - can this be done? I've tried assigning relationships but can't get it quite right as the duration is set - what is the easiest way of doing this?
Thanks!
Kate
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?