Task with linked start and finish dates

Kate NashMember for 15 years 3 months
Created
2
4
0

I need to put a task into a plan which starts on the date a predecessor finishes, and ends on the date a successor starts.

For example, the tasks I have are:

Handover to Client - Finish Milestone 1st December 2011

Rental Period

Handback from Client - Finish Milestone 31st December 2011

 

The Rental period needs to automatically show the start date as 1st December and the end date as 31st December - can this be done?  I've tried assigning relationships but can't get it quite right as the duration is set - what is the easiest way of doing this?

Thanks!

Kate

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Kate Welcome to Planning

    Hi Kate

    Welcome to Planning Planet

    Even in P6 this can be done.

    Insert a task called Rental Period between Handover to Client and Handback From Client

    Link FS between all 3 tasks

    Set the duration of the Rental Period task to end on 30 Dec 2011.

    Reschedule F9

    Best regards

    Mike Testro

    PS you only need to press the Save button once.

  2. 0
    Gary Whitehead ·

    Kate,   If you want the

    Kate,

     

    If you want the duration of the rental period to be defined by the milestones at either end, rather than being fixed, use a level of effort activity.

     

    Cheers,

     

    G