Revising the Updated program

Arun VasanthMember for 17 years
Created
8
4
0
Dear Friends I joined as a planner in a water pumping station project . My first task was to revise the delayed base program with out changein the Project finish dates. I changed some relations of the activities and I have completed that task. Now my real problem starts here.I dont want to delete the completed activities. The same actual dates I want to show as planned dates in my revised program.My intension is to show the planned bar and Acyual bar in same time. Dear Experts please help me in this issue ... Regards Arun .V

8 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Arun Set up a baseline /

    Hi Arun

    Set up a baseline / target programme that will underlay the live programme.

    Best regards

    Mike T.

  2. 0
    Arun Vasanth ·

    Dear Mike Thank you for

     

     

    Dear Mike

    Thank you for your reply.

    Aftr long time u r replying my Qurery

    But I didnt get you...

    Could u guide me through commends in Primavera P6 for same autal dates as base dates..

     

     

    Regards

    Arun V

  3. 0
    Jash Sales ·

    Hi Arun, In your case, you

    Hi Arun,

    In your case, you are revising your original baseline by reflecting your current actual dates and revised relationship of unfinished activities to recover your delay and this will need the approval from your client. 

    First, get an approval from your client and once you have it you can convert and assign ur updated schedule into baseline.

    Now, your question is, you want to show your planned bar similar to your actual bar? after you assinged your updated schedule as your new baseline, go to admin windows, click admin preference and go to earned value;  choose earned value calculation as "Budgeted values with current Dates".

    Gudluck,

    Jash

  4. 0
    Arun Vasanth ·

    Thank you Jash Jash I have

    Thank you Jash Jash I have revised the old updated program RV00. As every body knows there wont be change in the Actual dates .. Eg.. In ActivityID 1000 baseline start and finish is 10-10-2011 and 30 -10-2011 respectivley.But actual dates are 10-11-2011 and 30 -11-2011. In revesion 01 program I want 10-11-2011 and 30 -11-2011 as base program start date which is equal to Actual start.Is there any solution???? In the revised updated program I want the actual dates and Baseline line dates be same .....
  5. 0
    Jash Sales ·

    As I have said in my previous

    As I have said in my previous comments, you can use your updated programme as your revised baseline if your client approve it. modifying your baseline dates means you're revising it. why you dont just show your real delay in that particular activity; besides, your completion date in your updated programme is same as your baseline.

  6. 0
    Ferdinand U. ·

    hi arunJash already explained

    hi arun

    Jash already explained it, adjust the settings in admin menu

    remove your baseline first in maintain baseline, then create your baseline again in maintain baseline using your current project

    after assigning it, everything will be ok

  7. 0
    Jash Sales ·

    Thanks for the back-up

    Thanks for the back-up comment Sir Ferdie.

  8. 0
    Arun Vasanth ·

    Thanks    Jash & Friedieee...

    Thanks 

     

    Jash & Friedieee...

Log in or join to reply