Hi Guys , please I am battaling to produce a report that has the following

Project

       Resources  

          By Name                                    Hours - Monthly allocated

                                              Budgeted

                                              Remaining

 

Please assist

 

regards

1 reply

Oldest first
  1. 0
    Kannan CP ·

    Hi,   Go to Tools- Report

    Hi,

     

    Go to Tools- Report Wizard-New Report.

    Tick Time distributed data and select resources.

    Now you can select what u want to show in the report.

     

    Kannan