Skip to content

Earned value calculation

Kannan CPMember for 18 years 4 months
Created
5
1
0

Hi,

Is it possible to assign separate EV calculation method to different activities.

For eg:

Act1: Activity percent complete

Act2: 0/100 method

Act3: 50/50 method etc..

or only one method for the whole project?

5 replies

Oldest first
  1. 0
    Thaer Ghanim ·

    Hi  it is possible to assign

    Hi 

     

    it is possible to assign spearate EV Calaculation method to differnet WBS -Level .

    Open WBS-Window (Earned Value Tab from WBS Details)

  2. 0
    Thaer Ghanim ·

    Hi  it is possible to assign

    Hi 

     

    it is possible to assign spearate EV Calaculation method to differnet WBS -Level .

    Open WBS-Window (Earned Value Tab from WBS Details)

  3. 0
    Kannan CP ·

    Thanks Thaer...

    Thanks Thaer...

  4. 0
    Thaer Ghanim ·

    Welecom

    Welecom

  5. 0
    Syed Abrar ·

    Hi Taher,      Can u pls

     

    Hi Taher,
     
         Can u pls provide me  one case study for Earned value using WBS.
     
    Regards,
     
    Syed Abrar

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?