Skip to content

Percent Complete Conflict in Summary

Kashyap MothaliMember for 21 years 6 months
Created
0
2
0

In the P6 Projects Overview screen, the "Duration % of Original" value for my project is about 18%. I also performed the following calculation in excel by exporting the duration columns: (Planning Duration-Remaining Duration)/Planned Duration *100. The value here is only 3%.

Why is the summary % value different from the conventional formula - are both these not measuring the same?

 

The default Percent Complete Type is set to 'Duration' for all activities as well.

Thanks,

Kashyap

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?