how can get the planned%complete

Shima MemarMember for 14 years 10 months
Created
2
2
0

will someone please explain how can get the planned%complete in p6?

2 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·

    Hi Shima In P6 the 'Schedule

    Hi Shima

     

    In P6 the 'Schedule % Complete' gives the Planned % Complete.---You have to save a copy of the programme as Baseline to get the correct schedule % complete.

    Now at the activity level this % is based on durations. If you use the help hint the formula for calculation is clear...But at summary level the percentages are based on costs.

    ie.. Planned Value Cost / Budget at Completion,,,, where Planned Value cost for each activity= Shedule % * Budget for the activity.

    As such the  Schedule%  (Planned % ) can be compared to performance % complete and not to Duration % complete ---at summary levels.

     

    The other way around is to create a copy of the programme and auto update actuals and take the Duration complete. This Duration % complete can be used as a Planned % to compare with Actual % if you have not loaded cost as such could not get performance % complete.

    Now to combine both in the same layout is not possible as BL Duration % complete dont rollup at summary levels.

     

    Hope this helps.

     

    Regards

    Shareef

  2. 0
    Shima Memar ·

    thanks so much Shareef. It

    thanks so much Shareef. It was helpful.