Help With Out Of Sequence Logic

Simon CarterMember for 15 years 2 months
Created
3
4
0

Hi guys,

I'm looking for ideas about syntax to use with Primavera P6 to get all activities with out of sequence logic. We've to activities with FS lag to predecessor that's starting early creating high float. Anyone have any ideas?

Thanks,

Simon

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Simon,   Look at your

    Simon,

     

    Look at your schedule log -this will list all out of sequence activities for you.

     

    Cheers,

     

    G

  2. 0
    Ronald Winter ·

    Let me detail what Gary

    Let me detail what Gary said.  You need to go to the Schedule Screen (Tools / Schedule menu item or just, F9 Key) and click on the “Log to file” checkbox.  Ensure that the file name listed below is reasonable.  Now click on the Schedule button.

    Once done, go back to that same Screen (F9) and this time, click on the View Log button.  This will show you the schedule log.  In there is a section titled, "out-of-sequence activities."  It is not a particularly informative report (the P3 report was much better) but it is better than nothing.  Good luck!

  3. 0
    Simon Carter ·

    Thanks for the help

    Thanks for the help guys...certainly a lot easier than filtering :-)

    Simon