External Late Finish as a Constraint
In the Open Standard
Dattatreya PadharthiMember for 23 years 6 months
- Created
- 2
- 3
0
Hi Planners,
Wish you all a happy and prosperous new year!
We have copied multiple projects across to a different EPS node have links across Projects.
After Scheduling the new set of projects, we see negative floats of nearly 1500 days, bit of investigation shows constraint on some of the activities as External Late finish.
Has anyone come across this issue.
Regards
Datta
2 replies