Hi All,

 

I have a strange problem in P6 related to rebaselining the schedule using the current actual status as basis.

Following example illustrates the problem:

At data date planned percent complete for BL rev 0 = 50%, and actual percent complete = 30%.

While rebaselining, we decided to keep the BL 0 finish date, but would like to have P6 to re-distribute the remaining 70% of budgeted cost on the remaining 50% of the duration !

I would expect to see the new BL rev 1 with Schedule % (planned percent) complete = 30%, But P6 keeps displaying Sch % to be 50% because it still uses the duration % as basis !!

 

Anybody has had similar experience & has a possible workaround ?

 

Thanks

Sue

2 replies

Oldest first
  1. 0
    Andrew Podolny ·

    Hi Susan.That's how Primavera

    Hi Susan.

    That's how Primavera Calculates Scheduled Percent completion to date:

    The Schedule % Complete specifies how much of the activity’s original duration
    has been completed so far based on the baseline dates.
    PV = BAC * Schedule % Complete

    You can slightly shape the distribution using the resource loading curves but if you need the precise % on certain date - the only way I used is Future Buckets. Basically you have to manually distribute the units across timeframe:

    Then select to use future periods under WBS

    Now it's ready - you can attach it as new baseline. Here is my example:

    Hope it was helpful.

    Regards,

    Andrew

  2. 0
    Susan Young ·

    Hi Andrew,   Somehow I can't

    Hi Andrew,

     

    Somehow I can't view the snapshots you have attached. Could you please email me the solution at sussaa2001@hotmail.com

     

    Thanks

    Sue