Hi All,
I have a strange problem in P6 related to rebaselining the schedule using the current actual status as basis.
Following example illustrates the problem:
At data date planned percent complete for BL rev 0 = 50%, and actual percent complete = 30%.
While rebaselining, we decided to keep the BL 0 finish date, but would like to have P6 to re-distribute the remaining 70% of budgeted cost on the remaining 50% of the duration !
I would expect to see the new BL rev 1 with Schedule % (planned percent) complete = 30%, But P6 keeps displaying Sch % to be 50% because it still uses the duration % as basis !!
Anybody has had similar experience & has a possible workaround ?
Thanks
Sue