One activity code with more than on code value - P6 v7

Miguel CostaMember for 20 years 5 months
Created
2
2
0

Hi,

 

It's possible to have one activity code with two or more code values.

 

Example - In Activity code "REAL" you have the following codes values

a1

a2

a3

a4

a5

 For a particular activity you want to assign the activity code “Real” with the codes values of a1 and a2. For another activity you just want to assign it with code value a1.

 

This is possible to do in P6 V7?

 

Thanks,

MC

2 replies

Oldest first
  1. 0
    Mimoune Djouallah ·

    this not possible in any

    this not possible in any software, the code itseself should be unique, in your case you have to define another activity code beside real.

    HTH

  2. 0
    Anning Sofi ·

    Hi Miguel,For a given set of

    Hi Miguel,

    For a given set of code values, one code can only be assigned to the activity.

    Your intention was:

    Activity AAAAA (for example) = assign code REAL values a1, a2.

    This is not possible; either you assign one or the other only; which means code REAL = a1, or code REAL =a2;

     

    If you really need to have a code similar to REAL with your other code value, my suggesstion would be to replicate the code values of REAL to another code set, and then assign  the other code value to the activity.

     

     

     

     