Skip to content

Update Data date 1st time....

Jenny IngcoMember for 14 years 9 months
Created
4
1
0

Dear All....

I have a little problem with updating my schedule data date,, I start load the actual start date to my current schedule for some activities and then update the data data to the current date I moved it 4 monthes, the problem now I got very high -ve TF... So, I am very thankfull for any advises how I can fix that?

Thank you all..

4 replies

Oldest first
  1. 0
    Hilal Hallani ·

    Hello Hani, I had this same

    Hello Hani,

    I had this same problem when developing a programme. I had negative floats because my finish date in the programme did not match the "must finish by" date in the project details tab. When I changed the "must finish by" date in the project details tab to match the finish date in the actual programme, my negative floats changed to zero.

    Regards

    Hilal Hallani

  2. 0
    Hlamalani Baloyi ·

    can you really avoid negative

    can you really avoid negative float? i dont think you can, its a matter of a program telling you where you will not meet your finish date,

  3. 0
    Jenny Ingco ·

    Dear All,Thank you very much

    Dear All,

    Thank you very much for your great help. I did try to change the finish date of the project it's work ok for overall TF but still have -ve values for some WBS's and I don't want to change the duration also I am talking about 4000 activities. I got TF=-170 so how I can avoid that? Also, I need to know if that commen issue if I show the owner my current schedule with -ve TF?

    Thank you again,,

  4. 0
    Frederic Fasquelle ·

    Negative float can either

    Negative float can either come incorrect finish date of your project (as explained by Hilal), either you have put constarint.

    Primary constraints like Mandatory start/finish, "Start on", "Finish on" are deleting your float.

    It means that even if you have margin, by applying these constraints, P6 launch calculation considering them as 0 float. Any delay will thus generate negative float,

    Frederic

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?