Update Data date 1st time....
In the Open Standard
Jenny IngcoMember for 14 years 9 months
- Created
- 4
- 1
0
Dear All....
I have a little problem with updating my schedule data date,, I start load the actual start date to my current schedule for some activities and then update the data data to the current date I moved it 4 monthes, the problem now I got very high -ve TF... So, I am very thankfull for any advises how I can fix that?
Thank you all..