Skip to content

Update Progres option in P6 vs Update Progress option in P3

Raul SantosMember for 16 years 11 months
Created
3
5
0

When yo do Tools->Update Progress in P3, all your highlighted activities get actualized automatically. I did the same in P6, but the activities didn't get actualized automatically. Can anyone tell me if I'm missing any step or if I'm doing something wrong in P6? Thanks.

3 replies

Oldest first
  1. 0
    J Ks ·

    I think I'm having the same

    I think I'm having the same problem.  I move the data date, run "update progress" and the activies highlighted move out in time to the new DD.  It doesn't do this on all projects but just one right now.

     

    ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.

     

  2. 0
    Warren Sika ·

    Raul,Are you updating? Can

    Raul,

    Are you updating? Can you show the screen shot? Let's see what I can help.

    Warren

  3. 0
    Abilash Palakkadan Mathew ·

    Try the option apply actuals

    Try the option apply actuals and update progress. You have to have rights to actuals also check your rights also

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?