Calculate Finish Dates on P6.
In the Open Standard
Amir PezeshkMember for 14 years 10 months
- Created
- 3
- 2
0
Hi,
I give an example. Let's say i have an activity which start date is January 2, 2012 with 4 days duration finish date is January 6, 2012. The successor activity must start on January 7, 2012 with Finish to Start relationship. But all activities are starting at the same date of finishing date for Predecessors. Please help.
3 replies