question about data date

Alaa Al hajMember for 18 years 11 months
Created
2
1
0

hi

we are updaing the program on weekly basis - our cut off date is thursday

shall i use data date ( friday) in primavera 6 or thursday ?

 

thanks

Alaa

2 replies

Oldest first
  1. 0
    Ronald Winter ·

    The definition of a data date

    The definition of a data date is the first available hour for new work to commence or existing work to continue.  If your status is current as of Thursday at 16:00, then a data date of Friday at 08:00 might be appropriate.  Good luck!

  2. 0
    Ameen Pasha ·

    Absulately Correct.

    Absulately Correct.