Calculated Field

Mary Lou HortonMember for 15 years 11 months
Created
2
1
0

Can anyone tell me how to create a calculated field (like MS Project) in global change that will recaluate automatically (example as with BL Variance) so I do not need to recalc F9 every time. Thanks

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello,there is no such

    Hello,

    there is no such calculated fields in Primavera P6 client; you have to run global change to get the result

    or have a look at Primavera Web client calculated fields

    Alexandre

  2. 0
    Mary Lou Horton ·

    thanks Andre this is what I

    thanks Andre this is what I expected