Use of Steps
- Created
- 0
- 2
All
I have inherited a project where the tasks are very high level. I have a number of pipes listed under one task and I know the number of metres or feet to be installed in each. This is relatable to a budget labour unit so I have:
pipe 101 - 100 feet and 400 budget labour units
Pipe 102 - 200 feet and 350 budget labour units
Currently the task would have Budget labour units as 750. We get a report that says that 25 feet of pipe 101 is installed and maybe pipe 102 had 50 feet
Is there a way in the steps to represent this info
Thanks for your help
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?