Filter criteria for lags

Abhishek ChoubeyMember for 15 years 11 months
Created
1
1
0

Greetings of the day!!

 

Could any body please tell me about the filter criteria for activities having lags in Primavera 6..

 

Thanks & Regards,

Abhishek

1 reply

Oldest first
  1. 0
    Ron Beechey ·

    As far as I can tell there is

    As far as I can tell there is no field to select to create a Lag Filter. 