Actual cost and Earned value cost
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 7
- 3
0
Hi,
In my cost loaded schedule, the actual cost is showing some value higher than the earned value cost. So after each update to fix the problem, i make the actual cost similar to the earned value cost.
Is there any option to get the actual value similar to the earned value, based on the activity % progress.
Thanks in advance.
Regards
Kannan
7 replies
Oldest firstLog in or join to reply