Skip to content

0/100 Percent Complete

Clint MarquezMember for 17 years 10 months
Created
0
2
0

Hi to all!

I just encountered this kind of situation that's why I need some clarification and ideas regarding 0/100 Percent Complete.

What I know is that, 0/100 Percent Complete is applicable only for performance percent complete which is "Actual Progress or Earned Progress". So, Is this also applies in getting the planned value to date?

I always believe that whatever application we are going to use in getting actual progress must be the same method or system in getting a planned progress, and not to compare the apple to mango.

I hope to get help here in clarifying the issue.

 

Thank you & More Power to Everyone!

 

clintmarqz

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?