0/100 Percent Complete
- Created
- 3
- 2
Hi to all!
I just encountered this kind of situation that's why I need some clarification and ideas regarding 0/100 Percent Complete.
What I know is that, 0/100 Percent Complete is applicable only for performance percent complete which is "Actual Progress or Earned Progress". So, Is this also applies in getting the planned value to date?
I always believe that whatever application we are going to use in getting actual progress must be the same method or system in getting a planned progress, and not to compare the apple to mango.
I hope to get help here in clarifying the issue.
Thank you & More Power to Everyone!
clintmarqz
3 replies
Oldest firstLog in or join to reply