Fill down

Samey UddinMember for 14 years 3 months
Created
3
3
0

hii i want to know for waht purpose  does the option "filldown" is used for ,it will be better if someone can explain with an example ..

thanks

3 replies

Oldest first
  1. 0
    David Craig ·

    Hi Samey,This option is used

    Hi Samey,

    This option is used to duplicate other cells within your programme. It is pretty similar to Microsoft Excel. If you want to populate several activities with a different calendar for example, you would make sure the little highlight box was in the calendar you wanted to copy down, select the activites to change or add calendar to by using either Shift or Control, then right click on the mouse and select fill down. This will copy the calendar to all selected activities.

    I hope this helps!

    Regards,

    David Craig 

  2. 0
    xadlim B. ·

    you can use also short cut

     

    you can use also short cut for fill down CTRL+E

     

    Hope it helps......

  3. 0
    Samey Uddin ·

    thanx ..

    thanx ..