Skip to content

When I make down the original duration , the ressource allocation became overloaded but the unit/TIME didn't change

walid LahianiMember for 15 years 11 months
Created
6
4
0

Hello ,

Explication :

Imagine we have a Labour who works 8h/day and an excavation task ,

the original duration of the task is 10 days

so ,this laber will work a total of 80h ,

If i change the original duration to 2 days ,normally this laber have to work  40h/day => 5 labers/ day

But in the table we have always 8h/day (unit/time) =>one laber only

Thank you

 

 

6 replies

Oldest first
  1. 0
    Amit Parmar (PMP) ·

    Hi,Change "Duration Type" to

    Hi,

    Change "Duration Type" to "Fixed Units" in the activity and you would be able to see the changed rate. By default your "Duration Type" would be " Fixed Duration & Units".

     

    Duration Type follows following formula :

    • Remaining Duration = Remaining Units / Remaining Units/Time
    • (Original/Planned) Duration = (Budgeted/Planned) Units / (Budgeted/Planned) Units/Time

    hence changing the Duration Type affect the resource and duration calculations in the following ways :

     

      Duration Type
    Change UnitsChange Duration
      Change Units/Time
      Add 1st resource
      Add additional resources
      Fixed Units/Time
    DurationUnits
      Duration
      Units
      Duration
      Fixed Duration & Units/Time
    Units/TimeUnits
      Units
      Units
      Units
      Fixed Units
    DurationUnits/Time
      Duration
      Units
      Duration
      Fixed Duration & Units
    Unit s/TimeUnits/Time
      Units
      Units
      Units/Time of each Resource
  2. 0
    walid Lahiani ·

    Good morning Thank you for

    Good morning

    Thank you for this very interesting table

  3. 0
    Amit Parmar (PMP) ·

    Glad to be of help :)

    Glad to be of help :)

  4. 0
    Pei Tang ·

    i want to say "fixed duration

    i want to say "fixed duration and units" and "fixed units" should produce the same results.

  5. 0
    Bong Yagahon ·

    Hi,What is meant by

     

    Hi,

    What is meant by  "Explication"    as you telling in first line?

    ty.

  6. 0
    Bong Yagahon ·

    Hi,What is meant by

     

    Hi,

    What is meant by  "Explication"    as you telling in first line?

    ty.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?