Resource Loading using Import/Export

Alfon Lyndon JosonMember for 22 years 6 months
Created
0
3
0

Dear Team

I am having problems with Resource Loading using Import/Export. I am trying to Importi Resources and Roles, with Budget Labor Units and Budget Cost, but after the process, the entries for Resources and Roles are fine but the Budget Units are different, the Price/Unit is "0" as well as the Budget Cost shows "0".

Can anyone tell me how to do this correctly? I am using P6 release 6.0.

Regards

 

Alfon

Replies

Oldest first

No replies yet. Be the first to answer.