Level Of Effort progress updated

Izam ZakariaMember for 20 years 4 months
Created
1
2
0

Hi All,

Just wonder how normally you update your level of effort schedule activities (when you are running live schedule)? Do you change it to task dependent by the time the baseline been finalized?

1 reply

Oldest first
  1. 0
    Sm Pum ·

    Hi;Level Of effort is

    Hi;

    Level Of effort is dependant of the predecssor's and successor's completion.It will Complete with the completion of its successor.

     

    Regards