Update Progress Tool in P6
In the Open Standard
Alfredo VilaMember for 14 years 4 months
- Created
- 3
- 2
0
Hi planners.
I have a question about "Update Progress" tool in P6. I have a project on time but out of budget, so I want to update it using "Update Progress" only dates, not actual amount of resources because of resources must be update manually. However, "Update Progress" updates both at the same time, dates and actual resources amount
Is it possible to use this tool in order to update only date but not actual resources amount?.
Thanks a lot for your comments.
Alfredo
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?