Opening XER file from P6.r8 in P6.r7
In the Open Standard
Mohamed IbrahimMember for 20 years 10 months
- Created
- 3
- 2
0
Hi Everyone,
We are in transition period moving from P6r.7 to P6r.8.2 and we still have some project and 7 while we started some project in 8.
I am facing a problem in one my peoject where there is part of the project has been build in r.8 and I need to joined up the overall programme in r.7.
I did the standard XER file from 8 and when I upload it in r.7 doesn't work and I get the error message with this event code: CVRJC-3324-A .
I would appreciate any help or any recommendation on what I need to do on r.8 to get the xer file works in r.7
Kind Regards
Mohamed
3 replies
Oldest firstLog in or join to reply