Skip to content

Problem with Update Progress

Rajesh PassiMember for 14 years 1 month
Created
1
0

Hello Planners,

I had an issue with the update progress.

When i do update progress as on 31st Aug 23:59 actuals should be applied to all the activity started before 31st Aug 23:59 but i am facing a problem with this no actuals are applied.

Can anyone solve my query?

 

Thank you

Regards,

Rajesh.

1 reply

Oldest first
  1. 0
    Sm Pum ·

    If you are not mannually

    If you are not mannually Updating the Resources then make sure that "Auto compute actuals" option is checked.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?