Late start date equal to the actual start date ????
In the Open Standard
Susan YoungMember for 23 years 7 months
- Created
- 2
- 2
0
I have level of effort activities with resource assignments.
I have noticed that LOE’s that are in progress have the Late start date set equal to the Actual start date. This causes remaining late work to show up before the data date on histograms.
Is that a P6 bug ? Is there a way to solve this issue ?
Thanks
Sue