Late start date equal to the actual start date ????

Susan YoungMember for 23 years 7 months
Created
2
2
0

I have level of effort activities with resource assignments.

I have noticed that LOE’s that are in progress have the Late start date set equal to the Actual start date. This causes remaining late work to show up before the data date on histograms.

Is that a P6 bug ? Is there a way to solve this issue ?

 

Thanks

Sue
 

2 replies

Oldest first
  1. 0
    Susan Young ·

    Will really appreciate some

    Will really appreciate some feedback.

     

    Thanks

  2. 0
    Paul Harris ·

    Susan, there is not eniough

    Susan, there is not eniough information to understand your issue. It has been my experiance that P6 does not always calcuate negative dates correctly, but on the other hand you many be caught up by the dreaded "Planned Dates" issues.

     

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au - a Primavera scheduling software resources site

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?