Skip to content

Increase resourse limit.

Jenny IngcoMember for 14 years 9 months
Created
3
2
0

Dear All Planner..

What are the disadvantage from increasing the resourse limit to avoid showing resourse overallocation in the schedule?

Thank you,

HASAN

3 replies

Oldest first
  1. 0
    John Sims ·

    the answer is in your

    the answer is in your question really, by increasing the limit to avoid showing your current over alloaction will probley result in your activities not being carried out to the finish date you have planned, this will also result in the rise of allocated hours on each update.

    hope that helps.

    John

  2. 0
    Johannes Vandenberg ·

    Hi HasanI understand that you

    Hi Hasan

    I understand that you would like to increase the  resource limits because the display of over allocation is in some way bothering you.

    Why are you having  resources limits in you schedule? If you are not fully resourcing  you schedules and if you are not levelling the resources then i suggest that you delete this form your schedules.

    But if you use this functionality to allocate the available resources across projects whom are running at the same time then this is a powerful tool to use.

    To answer your question, overallocation is not advisable because proper resource levelling is not possible.

    Regards

    Johannes 

  3. 0
    Jenny Ingco ·

    Dear All, Thank you very much

    Dear All,

     

    Thank you very much for your replay..

     

    hanson

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?