Earned Value in P6

John SimsMember for 15 years 4 months
Created
2
2
0

Hi All,

Can anybody tell me what columns I should show when using EV in P6

Do i use planned cost or cum planned value cost?

I did think they was the same thing! But when exporting this data into an excel s curve chart my cum planned value is almost double of what my planned value is in my project in the month of October.

Anybody??

Cheers John

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    John,Cumulative planned cost

    John,

    Cumulative planned cost sums up the by period cost: by the end of week #2, cum cost equals week #1 + week #2 cost, and so on

    Planned cost displays the value by period

    it is therefore much better to export cost than cumulative cost; Excel will draw the S curve chart by agregating the individual values, on the contrary, if you want to produce a vertical bar chart in Excel, export the cumulative cost, as a bar chart is not cumulative by itself

    Alexandre

  2. 0
    John Sims ·

    Thanks Alexandra, you have

    Thanks Alexandra, you have been a great help!!