Weekly Reports
- Created
- 4
- 2
Afternoon all,
Quick query re reporting in P6..... Is it possible to run a report which shows all the activities that should have been progressed in the previous period but have not been?
I.E Basically at the moment I am filtering the P6 plan to show only those activities that should be progressed in the next 7 days. I then export this data to excel. The following week I then import my new progress into P6 and again export to excel. I then run a V-Lookup to highlight the variance in the 2 weeks which identifies any activities which should have progressed according to plan but has not been. Is there anything that can do this in P6?
Appreciate any input.
Cheers,
Rob