how to generate a planned vs actual curve basis on duration ?

Irfan KhanMember for 17 years 3 months
Created
2
2
0

I m working with a schedule wich is without cost & loaded

my duration % complete = 12.33 & my schedule % complete = 40% 
Keeping in view above percentage i would like to show curves on the basis of duration.
 
 
thanks in advance 

2 replies

Oldest first
  1. 0
    David Kelly ·

    By definition to draw a curve

    By definition to draw a curve you need two axis.  Typically in planning these axis are time and resource quantity/cost.

     

    if you want to use time for both axis, you need to add a resource that equals the time.  When you add a resource to an activity the default quantity is ususally 1h/h..... Therefore you need to add the same resource to every activity in the plan.  That means the resource qauntity will equal the duration.

    All P6's resource/earned curves will be based on the duration of the activities.

  2. 0
    Irfan Khan ·

    thanks.......got it

    thanks.......got it