Wronge start / finish date

Samer HozinMember for 15 years 9 months
Created
3
2
0

I set the project calender to 12 Hrs/ Day 7 Day/weeks and also the admin user pereference to 12 Hrs / day and check all user to specify the number of hous for each time period .

my problem is when I try to make - 6 hours lag for an activity it give me wronge start date for it

for example the activty by default start at 21 spep. 2PM and after assign -6 Hrs alg it start at 19 sep 10 AM ?

3 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Samer Welcome to Planning

    Hi Samer

    Welcome to Planning Planet.

    Why are you applying peculiar lags anyway?

    The correct linkage should be Finish Start between all tasks and that will solve your problems.

    21st September 2012 is a Friday so maybe you are linking back across an Islamic weekend.

    Best regards

    Mike Testro

  2. 0
    Samer Hozin ·

    Sir thank you for the

    Sir

    thank you for the replay

    I assign lag because i want to start the successor activty late by 6 hrs before other activity finsh and sure it FS also the project calender is 12 hrs / day 7days / week and not link to globe calender , so why this happens

  3. 0
    Raymund de Laza ·

    Set the New Created calendar

    Set the New Created calendar as your default calendar.