P6.8.2 Copying WBS and Activities from one project to another

Carumbaiah KollimadaMember for 15 years 9 months
Created
2
2
0

Hi,

I want to copy WBS from one project to another. I use the copy command and when I open the destination project the paste command isnt available. Does P6 allow us to copy WBS and activities? Help!

 

Regards,

Carum

2 replies

Oldest first
  1. 0
    Håkon Haukebøe ·

    Hi. Make sure you open both

    Hi. Make sure you open both the source and destination projects at the same time (ctrl click so both projects are selected in project view, then right click -> open project). In the wbs view you should now see wbs from both projects so you can move and copy between them.

     

    Haakon

  2. 0
    Carumbaiah Kollimada ·

    Thanks Haakon

    Thanks Haakon